DEME`s jack up vessel “Innovation” about to wrap up Hollandse Kust Noord V monopile installation with only 4 MP´s left on the quayside to install
Monopile installation at Hollandse Kust Noord V now looks like it will soon come to an end, with the Jack up vessel Innovation at the SIF fabrication facility at Maasvlakte 2 waiting for loading the last four TP-less monopiles for this project. On October 17th last year Innovation began piling the first monopile and if no complications occur Innovation could finish the piling this week making the project execution of piling just over 3 months to complete.